7.2 WxCC Migration Timeline

7.2.1 Overall Schedule

   WXCC MIGRATION - OVERALL TIMELINE
   WEEK   PHASE   ACTIVITIES
   *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *  *
   Week 1-2   PREPARATION   Training curriculum development
   Sandbox environment setup
   Final Chapter 6 validation
   Cutover runbook finalization
   Week 3-4   TRAINING   Wave 1 agent training (Chennai)
   (Wave 1)   Supervisor training
   UAT with business SMEs
   Week 5   WAVE 1 CUTOVER   Chennai (30 agents)
   (Pilot)   Weekend cutover
   5-day stabilization
   Week 6   TRAINING   Wave 2 agent training (London, NJ)
   (Wave 2)
   Week 7   WAVE 2 CUTOVER   London (15) + New Jersey (10)
   Weekend cutover
   5-day stabilization
   Week 8-9   TRAINING   Wave 3 agent training (Mumbai)
   (Wave 3)   120 agents - largest batch
   Week 10   WAVE 3 CUTOVER   Mumbai HQ (120 agents)
   (Final)   Weekend cutover
   24x7 operation - highest risk
   Week 11-12   HYPERCARE   Enhanced support
   Issue resolution
   Performance tuning
   Week 13   STABILIZATION   Handover to BAU operations
   UCCX decommission planning
   Project closure

7.2.2 Wave Migration Plan

Wave Site Agents Teams Weekend Risk Level
Wave 1 (Pilot) Chennai 30 Chennai_Support, India_Digital_Team Week 5 LOW
Wave 2 London + New Jersey 25 EMEA_Team, Americas_Team Week 7 MEDIUM
Wave 3 Mumbai HQ 120 India_Sales, India_Support, India_TechSupport, India_Billing Week 10 HIGH
TOTAL 4 Sites 175 8 Teams 3 Weekends

Wave Selection Rationale:

Wave Rationale
Wave 1 - Chennai Lowest risk: 30 agents, 9AM-9PM hours (not 24x7), single timezone, provides pilot learnings
Wave 2 - London/NJ Medium risk: 25 agents, business hours only, tests multi-region routing
Wave 3 - Mumbai Highest risk: 120 agents, 24x7 operation, primary support hub - benefits from Wave ½ learnings

7.2.3 Wave 1 Detailed Schedule (Chennai Pilot)

Day Date Activity Owner Hours
Pre-Week
Mon-Fri Week 3-4 Agent training (30 agents) Training Lead 2hr/day
Fri Week 4 Training completion sign-off Training Lead -
Fri Week 4 Go/No-Go decision call PM + Leads 30 min
Cutover Weekend
Fri 6:00 PM IST Cutover start - UCCX disable Voice Eng -
Fri 6:30 PM Entry Point DNS/routing switch Voice Eng -
Fri 7:00 PM Agent Desktop login validation CC Ops -
Fri 8:00 PM Test calls (all scenarios) QA 1 hr
Fri 9:00 PM Issue resolution window All 3 hr
Sat 9:00 AM Day 1 Live - first customer calls CC Ops -
Sat All day Enhanced monitoring Voice Eng + CC Ops 12 hr
Sun All day Stabilization Voice Eng 12 hr
Week 5 (Stabilization)
Mon-Fri Week 5 Production monitoring CC Ops -
Fri Week 5 Wave 1 sign-off CC Ops Manager -

7.2.4 Wave 2 Detailed Schedule (London + New Jersey)

Day Date Activity Owner Hours
Pre-Week
Mon-Fri Week 6 Agent training (25 agents) Training Lead 2hr/day
Fri Week 6 Go/No-Go decision call PM + Leads 30 min
Cutover Weekend
Sat 2:00 AM UTC Cutover start (off-hours all regions) Voice Eng -
Sat 2:30 AM Entry Point routing switch (EMEA/US) Voice Eng -
Sat 3:00 AM Agent Desktop login validation CC Ops -
Sat 4:00 AM Test calls (EMEA + Americas flows) QA 1 hr
Sat 9:00 AM UK Day 1 Live - London CC Ops -
Sat 9:00 AM ET Day 1 Live - New Jersey CC Ops -
Week 7 (Stabilization)
Mon-Fri Week 7 Production monitoring CC Ops -
Fri Week 7 Wave 2 sign-off CC Ops Manager -

7.2.5 Wave 3 Detailed Schedule (Mumbai HQ)

Day Date Activity Owner Hours
Pre-Week
Week 8-9 Agent training (120 agents - 4 batches) Training Lead 2hr/day
Fri Week 9 Training completion sign-off Training Lead -
Fri Week 9 Final Go/No-Go decision call PM + Leads 1 hr
Cutover Weekend
Sat 12:01 AM IST Cutover start (lowest call volume) Voice Eng -
Sat 12:30 AM India Entry Points routing switch Voice Eng -
Sat 1:00 AM Agent Desktop login (night shift) CC Ops -
Sat 2:00 AM Test calls (all India flows) QA 1 hr
Sat 3:00 AM Issue resolution window All 3 hr
Sat 6:00 AM Day shift handover CC Ops -
Sat-Sun All day Enhanced 24x7 monitoring Voice Eng + CC Ops 48 hr
Week 10 (Stabilization)
Mon-Fri Week 10 24x7 production monitoring CC Ops -
Fri Week 10 Wave 3 sign-off CC Ops Manager -