7.1 WxCC Migration Prerequisites

7.1.1 Phase 1 Dependency

   WXCC MIGRATION - PHASE 1 DEPENDENCY
   CRITICAL: UCCX REQUIRES CUCM FOR CTI CONNECTIVITY
   DEPENDENCY CHAIN:
   CTI (JTAPI)
   UCCX <-> CUCM
   (Contact   (Call
   Center)   Control)
   MIGRATION IMPACT:

   Once CC agents move to   Once CUCM is decommissioned,
   Webex Calling (Phase 1   UCCX loses CTI connectivity.
   Batch 5), they cannot   No parallel operation possible.
   receive UCCX routed calls.
   IMPLICATION:
   WxCC cutover is effectively a BIG BANG for contact center.
   Phase 1 completion is a HARD GATE for Phase 2.
   Rollback = Full stack rollback (Webex Calling   CUCM   UCCX)

7.1.2 Prerequisites Checklist

   WXCC MIGRATION - PREREQUISITES CHECKLIST
   PHASE 1 COMPLETION (MANDATORY)
   [ ] All 175 CC agents migrated to Webex Calling (Chapter 7 P1 Batch 5)
   [ ] CC agent desk phones registered to Webex Calling
   [ ] Webex App deployed to all CC agents
   [ ] PSTN connectivity validated (LGW India, CCPP EMEA/US)
   [ ] Phase 1 48-hour stability confirmed for CC agents
   [ ] CUCM decommission NOT started (rollback path preserved)
   CHAPTER 6 IMPLEMENTATION (MANDATORY)
   [ ] WxCC tenant activated (India DC)
   [ ] All 175 agent licenses assigned
   [ ] 6 Entry Points configured
   [ ] 10 Queues configured
   [ ] 18 Skills created
   [ ] 12 Skill Profiles created
   [ ] 8 Teams configured
   [ ] 9 Flows built and validated
   [ ] 87 Audio prompts uploaded (62 EN + 25 HI)
   [ ] Virtual Agent "Abhi" integrated (Dialogflow CX)
   [ ] Salesforce connector configured
   [ ] Recording enabled (100% all calls)
   [ ] PCI auto-pause configured (Billing queue)
   [ ] All 20 test scenarios passed (Chapter 6.10.2)
   INFRASTRUCTURE
   [ ] DNS entries prepared for cutover
   [ ] Toll-free number porting request submitted (if applicable)
   [ ] SD-WAN QoS validated (ABV-SDWAN-2024)
   [ ] India DC data residency confirmed
   TRAINING
   [ ] Agent training curriculum finalized
   [ ] Supervisor training curriculum finalized
   [ ] Training environment provisioned (sandbox tenant)
   [ ] Training schedule published
   OPERATIONS
   [ ] Cutover runbook reviewed and signed off
   [ ] Rollback procedures documented
   [ ] Hypercare support schedule confirmed
   [ ] Help desk briefed on WxCC support
   [ ] Vendor TAC cases opened (preventive)

7.1.3 Go/No-Go Gate

Gate Criteria Owner Status
G1 Phase 1 CC agents stable 48+ hours Voice Eng Lead [ ]
G2 Chapter 6 implementation 100% complete WxCC Eng Lead [ ]
G3 All 20 test scenarios passed QA Lead [ ]
G4 Agent training 100% complete (per wave) Training Lead [ ]
G5 Cutover runbook signed off Project Manager [ ]
G6 Rollback plan validated Voice Eng Lead [ ]
G7 Business owner approval CC Operations Mgr [ ]
G8 No P1/P2 open defects QA Lead [ ]

Decision: All gates MUST be passed before cutover proceeds.