7.1 WxCC Migration Prerequisites¶
7.1.1 Phase 1 Dependency¶
WXCC MIGRATION - PHASE 1 DEPENDENCY
CRITICAL: UCCX REQUIRES CUCM FOR CTI CONNECTIVITY
DEPENDENCY CHAIN:
CTI (JTAPI)
UCCX <-> CUCM
(Contact (Call
Center) Control)
MIGRATION IMPACT:
Once CC agents move to Once CUCM is decommissioned,
Webex Calling (Phase 1 UCCX loses CTI connectivity.
Batch 5), they cannot No parallel operation possible.
receive UCCX routed calls.
IMPLICATION:
WxCC cutover is effectively a BIG BANG for contact center.
Phase 1 completion is a HARD GATE for Phase 2.
Rollback = Full stack rollback (Webex Calling CUCM UCCX)
7.1.2 Prerequisites Checklist¶
WXCC MIGRATION - PREREQUISITES CHECKLIST
PHASE 1 COMPLETION (MANDATORY)
[ ] All 175 CC agents migrated to Webex Calling (Chapter 7 P1 Batch 5)
[ ] CC agent desk phones registered to Webex Calling
[ ] Webex App deployed to all CC agents
[ ] PSTN connectivity validated (LGW India, CCPP EMEA/US)
[ ] Phase 1 48-hour stability confirmed for CC agents
[ ] CUCM decommission NOT started (rollback path preserved)
CHAPTER 6 IMPLEMENTATION (MANDATORY)
[ ] WxCC tenant activated (India DC)
[ ] All 175 agent licenses assigned
[ ] 6 Entry Points configured
[ ] 10 Queues configured
[ ] 18 Skills created
[ ] 12 Skill Profiles created
[ ] 8 Teams configured
[ ] 9 Flows built and validated
[ ] 87 Audio prompts uploaded (62 EN + 25 HI)
[ ] Virtual Agent "Abhi" integrated (Dialogflow CX)
[ ] Salesforce connector configured
[ ] Recording enabled (100% all calls)
[ ] PCI auto-pause configured (Billing queue)
[ ] All 20 test scenarios passed (Chapter 6.10.2)
INFRASTRUCTURE
[ ] DNS entries prepared for cutover
[ ] Toll-free number porting request submitted (if applicable)
[ ] SD-WAN QoS validated (ABV-SDWAN-2024)
[ ] India DC data residency confirmed
TRAINING
[ ] Agent training curriculum finalized
[ ] Supervisor training curriculum finalized
[ ] Training environment provisioned (sandbox tenant)
[ ] Training schedule published
OPERATIONS
[ ] Cutover runbook reviewed and signed off
[ ] Rollback procedures documented
[ ] Hypercare support schedule confirmed
[ ] Help desk briefed on WxCC support
[ ] Vendor TAC cases opened (preventive)
7.1.3 Go/No-Go Gate¶
| Gate | Criteria | Owner | Status |
|---|---|---|---|
| G1 | Phase 1 CC agents stable 48+ hours | Voice Eng Lead | [ ] |
| G2 | Chapter 6 implementation 100% complete | WxCC Eng Lead | [ ] |
| G3 | All 20 test scenarios passed | QA Lead | [ ] |
| G4 | Agent training 100% complete (per wave) | Training Lead | [ ] |
| G5 | Cutover runbook signed off | Project Manager | [ ] |
| G6 | Rollback plan validated | Voice Eng Lead | [ ] |
| G7 | Business owner approval | CC Operations Mgr | [ ] |
| G8 | No P1/P2 open defects | QA Lead | [ ] |
Decision: All gates MUST be passed before cutover proceeds.